A building or structure's soundness starts 
			with a strong foundation, especially the piles.  As a part of 
			foundation's quality assurance, Maintain Load Test, also known as 
			Static Load Test is necessary to ensure the pile that was driven 
			could take the design load of the structure.  During this test, 
			load would be applied on the selected pile and the pile settlement 
			under the acting load would be recorded.  As a common practice, 
			pile would be loaded up to twice of the working load, which is 
			regarded as the Test Load of the pile.
			
			 Prior testing, the pile head shall be cut off 
			or built up to the necessary elevation and shall be capped 
			appropriately to produce a bearing surface perpendicular to the axis 
			of the pile. The arrangement shall be such that none of the test 
			load is carried by the ground under the cap.
			
			The test load shall be applied in one of the 
			following ways
			
				- 
				
				By means of a jack which obtains its 
				reaction from kentledge heavier than the required load; 
- 
				
				By means of a jack which obtains its 
				reaction from tension piles or other suitable anchors.
 
 
			The load shall be measured using a calibrated 
			load gauge and also a calibrated pressure gauge in the hydraulic 
			system. The jack and load gauge shall be carefully aligned so that 
			the load applied is co-axial with the pile.  When method (1) is 
			used, care shall be taken to ensure that the centre of gravity of 
			the kentledge is on the axis of the pile. The nearest edge of the 
			crib supporting the kentledge stack shall not be closer than 1.3 m 
			to the surface of the test pile.  Kentledge shall not be used 
			for testing raked piles.  When method (2) is used, all anchor 
			piles shall be at a distance of at least three (3) pile shaft 
			diameters from the test pile, centre to centre, and in no case shall 
			they be less than 2 m from the test pile.  If the anchor piles 
			are to be permanent working piles, their levels shall be  
			observed during application of the test load to ensure no residual 
			uplift occurs.
			
			Settlements shall be measured by use of a 
			reference beam or wire supported independently of the load test 
			pile, reaction pile or piles supporting reaction loads. Settlements 
			shall be measured to the nearest 0.1 mm for reference beams or 0.5 
			mm for reference wires. The reference beam supports shall be located 
			at least 3 m from the load test pile, reaction pile or piles 
			supporting reaction loads. The reference beams or wires shall be 
			protected from the effects of temperature changes.
			
			The Maintained Load Test shall be carried out 
			as follows unless alternative method specified by the Consultants;
			a) The full test load on a pile shall be twice the design load noted 
			on the
			Drawings and it shall be applied in twelve equal decrements. At 
			least two
			hours shall elapse between the addition of each load increment, i.e. 
			until the rate of settlement is reduced to less than 0.25 mm/hour 
			and slowing down;
			b) The full test load shall be maintained on the pile for at least 
			48 hours and settlements shall be recorded at intervals of not more 
			than 12 hours. The test pile shall then be unloaded in four equal 
			decrements at one-hour intervals until the full load is removed. 
			Settlement readings shall be made immediately after and before every 
			load increment is applied or removed.